Occupancy Permit, Locational Clearance and Zoning Clearance: What Comes First

By , Chartered Accountant

Published · Updated

PD 1096 (National Building Code) Sec. 309 · JMC 2018-01

Updated 21 November 2026

How soon must the Building Official issue a certificate of occupancy?

30 daysafter the final inspection

Once the building passes the final inspection and the certificate of completion is filed, the Building Official issues the certificate of occupancy within 30 days; simple buildings get it within 5 working days.

  • The order: locational → building → occupancy — then the business permit
  • Simple applications: 5 working days each — building permit and occupancy (JMC 2018-01)

Locational

Zoning office

of the city or municipality

Building permit

Building Official

PD 1096 Sec. 301

Occupancy

Building Official

PD 1096 Sec. 309

Source: PD 1096 Secs. 301, 304, 309 (archived Official Gazette text); JMC 2018-01 Secs. 6.1.7, 6.1.14, 6.2.12. As of November 2026.

On this page (9)
  1. Locational clearance vs building permit vs occupancy permit
  2. The sequence: what comes first
  3. Requirements for each permit
  4. Tenants: what to ask the landlord for
  5. Home-based businesses and zoning
  6. Fees and penalties
  7. Common problems
  8. Frequently asked questions
  9. Sources and references

Quick answer

Three permits, in order. First the locational (zoning) clearance from the city's zoning office confirms the use is allowed at that site; it is a requirement of the building permit (JMC 2018-01). Then the building permit from the Building Official, issued within 15 days of paying the fees (PD 1096 Sec. 304). After construction and final inspection, the certificate of occupancy, issued within 30 days (Sec. 309) — 5 working days for simple buildings. No building may be used without it, and a business permit may require it.

What you need to know

  • Zoning comes first: the Building Official checks zoning and land use before issuing a building permit (Sec. 303).
  • A building permit lapses if work does not start within one year, or stops for 120 days (Sec. 305).
  • Changing the use of a building, for example from house to shop, needs a new certificate of occupancy (Sec. 309).
  • Tenants: ask the landlord for the occupancy permit and the building's fire safety certificate before signing.
  • Simple applications (up to 1,500 sq m, small buildings) take 5 working days each under JMC 2018-01.

At a glance

Who needs it
Anyone building, altering or changing the use of a building; tenants rely on the owner's
Cost
Building Official's and zoning fees under the Code's schedule and local ordinance
Deadline
Before construction (building permit) and before use (occupancy)
Where
City or municipal one-stop shop for construction permits (zoning, OBO, BFP)
Processing time
Simple: 5 working days each; Code limits 15 and 30 days
Official link
PD 1096 · JMC 2018-01

Locational clearance vs building permit vs occupancy permit

Locational / zoning clearanceBuilding permitCertificate of occupancy
What it isConfirms the use is allowed in that zonePermission to build, alter, repair, move or demolishPermission to use or occupy the finished building
Issuing officeZoning office (zoning administrator / planning office)Office of the Building Official (OBO)Office of the Building Official
Legal basisLocal zoning ordinance; required for the building permit (JMC 2018-01 Sec. 6.1.7)PD 1096 Secs. 301–305PD 1096 Sec. 309
WhenBefore the building permit, and for a business permit in a new locationBefore any construction workAfter construction, before anyone uses the building
Time limitPart of the one-stop process15 days after fees are paid (Sec. 304); 5 working days if simple30 days after final inspection (Sec. 309); 5 working days if simple
Fire clearance alongside—Fire safety evaluation clearance (FSEC): 3 working daysFire safety inspection certificate (FSIC): 3 working days

PD 1096; JMC 2018-01 Secs. 6.1.14, 6.2.12. "Locational clearance" and "zoning clearance" are used for the same certificate in many cities.

The sequence: what comes first

From empty lot to open shop

  1. 1Locational (zoning) clearance

    Zoning office confirms the use fits the zone.

  2. 2Building permit + FSEC

    OBO and BFP review the plans; 5 + 3 working days if simple.

  3. 3Construction

    Must start within 1 year; no stop longer than 120 days.

  4. 4Certificate of completion → final inspection

    OBO, with electrical and other inspections.

  5. 5Certificate of occupancy + FSIC

    5 + 3 working days if simple; 30 days at most.

  6. Owner occupies

    1. Business permit

      Occupancy permit shown if the city asks.

    Owner leases out

    1. Tenant's business permit

      Tenant relies on the owner's occupancy permit and FSIC.

PD 1096 Secs. 301, 303–305, 309; JMC 2018-01 Secs. 6.1.7, 6.1.14, 6.2.3(c), 6.2.12, 7.3 (at most four steps for each application).

Maximum processing times

Simple applications under JMC 2018-01 vs the National Building Code's outer limits

Days
ItemDays
Building permit, simple (JMC 2018-01)5 working days
Fire safety evaluation clearance (BFP)3 working days
Building permit after payment (PD 1096 Sec. 304)15 days
Occupancy, simple (JMC 2018-01)5 working days
Fire safety inspection certificate (BFP)3 working days
Occupancy after final inspection (Sec. 309)30 days
JMC 2018-01 Secs. 6.1.14, 6.2.12; PD 1096 Secs. 304, 309.

Requirements for each permit

PermitMain documentsBasis
Locational clearanceApplication, site plan or vicinity map, proof of ownership or lease, description of the intended useLocal zoning ordinance (lists vary)
Building permitApplication forms, plans signed by licensed professionals, proof of ownership, locational clearance, FSECPD 1096 Secs. 301, 303; JMC 2018-01 Sec. 6.1.7
Certificate of occupancyApplication, certificate of completion, as-built plans if changed, locational clearance copy, FSICPD 1096 Sec. 309; JMC 2018-01 Sec. 6.2.3(c)

JMC 2018-01 confirms the locational clearance as a requirement of both the building permit and the certificate of occupancy; the other items vary by city.

Occupancy permit checklist (owner or developer)

0 of 7 ticked · ticks are kept in this browser tab only

Tenants: what to ask the landlord for

Ask forWhy
Certificate of occupancy for the unit or buildingNo building may be used without it (Sec. 309), and some cities require it for your business permit
The occupancy's allowed useA residential occupancy may not cover a shop; changing the use needs a new certificate
Building's FSIC for occupancyYour business FSIC can build on it (RA 9485 Sec. 12(b))
Lease that describes the property and allows business useCities such as Quezon City ask for it with the permit
Zoning confirmation for your type of businessThe zoning office can refuse a use the ordinance does not allow

Home-based businesses and zoning

Whether you may run a business from home depends on your city's zoning ordinance, not national law. Many ordinances allow light home occupations in residential zones and refuse uses with noise, traffic or hazardous materials. Ask the zoning office before you register the business at your home address, and keep the owner's written consent if you rent.

Fees and penalties

ItemWhat appliesBasis
Building permit and occupancy feesBuilding Official's fees under the National Building Code schedule, plus local feesPD 1096 and its IRR; local ordinance
Zoning / locational clearance feeSet by the city's zoning ordinanceLocal ordinance
Fire safety fees15% of the building official's fees (occupancy FSIC), minimum ₱500Fire Code RIRR Sec. 12.0.0.4
Building used without an occupancy certificateProhibited; the Building Official may stop its use, and fines apply under PD 1096 and local ordinancesPD 1096 Sec. 309
Work without a building permitProhibited; work may be stopped and fines applyPD 1096 Sec. 301

The National Building Code IRR fee schedule and DHSUD's locational clearance rules were not checked for this page, so no amounts are quoted; the city's assessment governs.

Common problems

ProblemFix
Zoning refuses the business useAsk about a variance or exception under the ordinance, or find a site in a commercial zone
Building permit expired before constructionIt lapses after one year without work or 120 days of stoppage (Sec. 305); apply again
Shop in a building with no occupancy permitAsk the owner to secure it; your permit may be held up
Converted a house into a storeApply for a new certificate of occupancy for the change of use (Sec. 309)
Only part of the building is finishedA partial certificate of occupancy is possible, with an FSIC for that part (JMC 2018-01 Sec. 6.2.9)

Buod sa Tagalog

Tatlong permit, ayon sa pagkakasunod-sunod: una ang locational o zoning clearance mula sa zoning office ng lungsod, na nagpapatunay na pinapayagan ang gamit sa lugar; sunod ang building permit mula sa Building Official, sa loob ng 15 araw matapos magbayad; at pagkatapos ng konstruksyon at final inspection, ang certificate of occupancy sa loob ng 30 araw, o 5 araw ng trabaho para sa simpleng gusali. Walang gusaling maaaring gamitin nang walang certificate of occupancy.

Frequently asked questions

+What are the requirements for an occupancy permit?

The application, a certificate of completion, as-built plans if the work changed, a copy of the locational clearance and the BFP's fire safety inspection certificate for occupancy, after the Building Official's final inspection. JMC 2018-01 lists the locational clearance copy; cities add their own forms and fees.

+How long does it take to get an occupancy permit?

The National Building Code gives the Building Official 30 days after the final inspection and the certificate of completion (PD 1096 Sec. 309). For simple applications, JMC 2018-01 sets a maximum of five working days, with the BFP's fire safety inspection certificate within three working days.

+What is the difference between a building permit and an occupancy permit?

A building permit lets you start construction, alteration or demolition and must be obtained first (PD 1096 Sec. 301). A certificate of occupancy lets you use the finished building and is issued only after the final inspection shows the work follows the Code and the approved plans (Sec. 309).

+Can I move in or rent out a building without an occupancy permit?

No. PD 1096 Sec. 309 says no building may be used or occupied, and no change in its use made, until the Building Official issues a certificate of occupancy. A tenant should ask the landlord for it, because a business in an unpermitted building can have its own permit held up.

+What is a locational clearance and where do I get it?

A locational clearance, also called a zoning clearance, is the city's confirmation that a project or business is allowed in that zone under the local zoning ordinance. Get it from the city or municipal zoning office, usually through the one-stop shop. It is a requirement of the building permit under JMC 2018-01.

+Is a locational clearance the same as a zoning clearance?

In most cities, yes: both names describe the zoning office's certificate that the intended use conforms to the zoning ordinance. Some cities issue it at two points, for a construction project and for a business in an existing building, so ask which one your application needs.

+Do I need a locational clearance for a business permit?

Usually, for a new business or a new location: the zoning office checks the use as part of the business one-stop shop under RA 11032. For renewals at the same address with the same use, cities generally do not ask again. Check your city's business permit checklist.

+Do I need a new occupancy permit after a renovation or change of use?

A change in the use or occupancy classification needs a new certificate of occupancy under PD 1096 Sec. 309, for example turning a house into a store. Renovation work itself needs a building permit first (Sec. 301), and the Building Official inspects it before the building is used again.

+How much does an occupancy permit cost?

The Building Official charges the fees in the National Building Code's schedule, the city adds its own local fees, and the BFP charges 15% of the building official's fees, at least ₱500, for the fire safety inspection certificate. Because the schedule depends on the building's size and type, ask the one-stop shop for an assessment.

+Does an occupancy permit expire?

A certificate of occupancy covers the building as built and used. It stays in force until the building is altered or its use or occupancy classification changes, which needs a new certificate under PD 1096 Sec. 309. The business inside renews its own permit and fire safety certificate every year.

Sources and references

Next step

Building cleared? Apply for the business permit.

Related guides and tools

Cite this page

Deepak Middha. "Occupancy Permit, Locational Clearance and Zoning Clearance: What Comes First." Sulat.ph, updated November 21, 2026. https://sulat.ph/business/how-to/occupancy-permit-locational-clearance

Free to quote with a link. For fees and deadlines, cite the law or the city ordinance named in the sources, with its date.

Author and editorial review

, Chartered Accountant

Chartered Accountant with 18 years in hedge funds; writes and maintains sulat.ph. Every rate, ceiling, deadline and fee on this page is taken from the law, agency issuance or official local government page named in the sources and was checked against that source on November 21, 2026. Where a figure could not be confirmed officially, the page says so.

Author of The Complete Fund Accounting Handbook in the Sulat.ph Library

Spotted an error or an outdated rule? Send a correction.

Sulat.ph is not a law firm and does not provide legal advice. AI-generated drafts should be reviewed by a qualified Philippine lawyer before formal use.