FSIC for occupancy vs FSIC for business permit
| FSIC for certificate of occupancy | FSIC for business permit | |
|---|---|---|
| When | After construction, before the building is used (occupancy permit) | Every new business permit and every renewal |
| Fee | 15% of all fees charged by the Office of the Building Official, minimum ₱500 | 15% of all fees charged by the LGU, minimum ₱500 |
| Processing | At most 3 working days within the occupancy process (JMC 2018-01) | At most 7 working days; 3 on renewal (RA 11032) |
| Who applies | Building owner or developer | The business operating in the building |
| Link between them | Issued first | For a new business, the occupancy-stage FSIC is enough basis (RA 9485 Sec. 12(b)) |
RIRR Sec. 12.0.0.4(A)(1)(a)–(b); JMC 2018-01 Sec. 6.2.12; RA 11032 (new Sec. 12 of RA 9485). A third kind, for PEZA annual inspection, also exists.
FSIC requirements
| Item | Occupancy FSIC | Business FSIC | Basis |
|---|---|---|---|
| Inspection by the BFP | Yes | Yes (new and renewal) | RA 9514 Sec. 7(a) |
| Fire code fees paid | Yes | Yes | RIRR Sec. 9.0.2.4(A)(3) |
| Fire safety maintenance report (FSMR) | — | If applicable to the building | RIRR Sec. 9.0.2.4(A)(3) |
| Fire safety evaluation clearance (FSEC) | From the building permit stage | — | RA 9485 Sec. 12(a) |
| Certificate of completion | Yes | — | PD 1096 Sec. 309 |
| Business permit assessment (fee base) | — | Yes | RIRR Sec. 12.0.0.4 |
| Other documents | Per the BFP Citizen's Charter | Per the BFP Citizen's Charter | RIRR Sec. 9.0.4.2 |
The RIRR sends the document list to the BFP Citizen's Charter; ask the BFP desk at your city's one-stop shop for the current one.
How the FSIC process works
From application to certificate, and what happens on failure
1Apply with the business permit
BFP desk at the one-stop shop assesses and collects the fee.
2Inspection
Exits, alarms, extinguishers, wiring, hazardous materials.
Passed
FSIC issued
Within 7 working days (3 on renewal).
Business permit released
Failed
Notice to comply
Then "FIRE HAZARD" sign, notice to correct, abatement order.
Closure order if still not corrected
FSIC fee computation with a worked example
- 1
- 2
- 3
- 4
FSIC fee at different levels of city fees
15% of all LGU fees, minimum ₱500
| Item | FSIC fee |
|---|---|
| City fees ₱1,000 | ₱500 |
| City fees ₱3,000 | ₱500 |
| City fees ₱5,000 | ₱750 |
| City fees ₱10,000 | ₱1,500 |
| City fees ₱20,000 | ₱3,000 |
| City fees ₱40,000 | ₱6,000 |
Fire safety inspection checklist
Get ready for the BFP inspection
0 of 10 ticked · ticks are kept in this browser tab only
Equipment
Exits
Housekeeping
Built from RA 9514 Sec. 7; the BFP inspector uses the BFP's own checklist, which can include more items for your type of occupancy.
Failed inspection, penalties and closure
| Stage | What the BFP does | Time given |
|---|---|---|
| Notice to comply | Lists the violations to fix | Up to 15 days |
| Still not fixed | Posts a "FIRE HAZARD" sign, imposes an administrative fine, issues a notice to correct | Up to 15 days |
| Abatement order | Orders the hazard removed | Up to 15 days |
| Closure order | Closes the establishment; tells the mayor and BPLO to revoke the business permit; revokes any FSIC | Immediate on service |
RIRR Sec. 13.0.0.4; RA 9514 Sec. 9 (closure "notwithstanding any permit clearance or certificate earlier issued by the local authorities").
| Violation | Penalty | Basis |
|---|---|---|
| Non-compliance with the Fire Code | Administrative fine up to ₱50,000, or stoppage of operations or closure | RA 9514 Sec. 11(1)(a) |
| Willful failure to correct a violation | 6 months to 6 years' imprisonment, or a fine up to ₱100,000, or both | RA 9514 Sec. 11(1)(b) |
| Failure to renew the FSIC, under a year | 50% of the total amount payable | RIRR fine schedule |
| Failure to renew the FSIC, a year or more | 100% of the total amount payable, for each year of default | RIRR fine schedule |
Common FSIC problems
| Problem | Fix |
|---|---|
| Business permit held up for the FSIC on renewal | If the BFP does not present it within 3 working days, the business is deemed to have a temporary valid FSIC (RA 9485 Sec. 12(d)) |
| Extinguisher expired or uncharged | Have it recharged and tagged before the inspection |
| Building has no occupancy FSIC | Ask the building owner; the occupancy-stage FSIC is the basis for yours |
| Food business | The sanitary permit inspection is separate; prepare for both |
| Fee seems too high | Check the base: 15% of the city's fees, not of your sales |
Buod sa Tagalog
Ang fire safety inspection certificate (FSIC) ay mula sa Bureau of Fire Protection matapos ang inspeksyon, at walang occupancy permit o business permit na maibibigay kung wala ito. May dalawang pangunahing uri: para sa occupancy at para sa business permit. Ang bayad para sa negosyo ay 15% ng lahat ng bayaring sinisingil ng lungsod, at hindi bababa sa ₱500. Dapat itong ibigay sa loob ng 7 araw ng trabaho, at 3 araw kapag renewal. Kapag bumagsak sa inspeksyon, may abiso at maaaring humantong sa pagpapasara.
Frequently asked questions
+What are the FSIC requirements for a business permit?
A BFP inspection, payment of the fire code fees and, where your building needs one, a fire safety maintenance report, under the 2019 Fire Code rules. For a new business, the FSIC issued when the building got its occupancy permit is the basis. The full document list is in the BFP Citizen's Charter.
+How much is the FSIC fee?
For a business permit, 15% of all the fees the local government charges you, but never less than ₱500, under Sec. 12.0.0.4 of the 2019 Revised IRR of the Fire Code. If your city's fees total ₱3,800, the FSIC fee is ₱570. For occupancy it is 15% of the building official's fees, also with a ₱500 minimum.
+How long is an FSIC valid?
The Fire Code rules tie the FSIC for business to each business permit application and renewal, and business permits are valid for one year under RA 11032. In practice you renew the FSIC every year with your permit. The fine schedule charges 50% of the fees for missing a renewal by less than a year.
+How do I renew my FSIC?
Renew it with your business permit at the city's one-stop shop, where the BFP collects the fee. RA 11032 gives the BFP three working days on renewal; if it does not present the FSIC in time, the business is deemed to have a temporary valid FSIC so the permit can be renewed.
+What is the difference between FSEC and FSIC?
The fire safety evaluation clearance (FSEC) is issued at the building permit stage, after the BFP reviews the plans. The fire safety inspection certificate (FSIC) is issued after the BFP inspects the finished building or the operating business. RA 11032 caps both at seven working days.
+What happens if I fail the fire safety inspection?
The BFP issues a notice to comply giving up to 15 days. If the violations are not fixed, it posts a fire hazard sign, fines you and issues a notice to correct, then an abatement order. If you still do not comply, it closes the establishment and asks the city to revoke your business permit.
+Do sari-sari stores and home businesses need an FSIC?
Yes, if they apply for a business permit: RA 9514 Sec. 5(g) bars any business permit or permit to operate without an FSIC. Small establishments usually get a simple inspection and pay the ₱500 minimum, because 15% of a small store's city fees is usually less than that.
+What is the penalty for operating without an FSIC?
Non-compliance with the Fire Code carries an administrative fine of up to ₱50,000 or stoppage of operations or closure. Willfully failing to correct a violation can lead to six months to six years of imprisonment or a fine of up to ₱100,000, or both, under RA 9514 Sec. 11.
Sources and references
- RA 9514 Fire Code of the Philippines — Secs. 5(g), 7, 9, 11 (checked November 21, 2026)
- 2019 Revised IRR of RA 9514 (archived official BFP copy) — Secs. 9.0.2.4, 12.0.0.2, 12.0.0.4, 13.0.0.4; fine schedule (checked November 21, 2026)
- BFP MC 2021-020 (archived official copy) — fire code fee guidelines (checked November 21, 2026)
- RA 11032 (Ease of Doing Business Act) — new Sec. 12 of RA 9485: FSEC and FSIC processing (checked November 21, 2026)
- DILG-DPWH-DICT-DTI JMC 2018-01 (archived) — FSIC for occupancy within 3 working days (checked November 21, 2026)
Next step
FSIC sorted? Check the occupancy permit and zoning next.
Related guides and tools
Cite this page
Deepak Middha. "Fire Safety Inspection Certificate (FSIC): Requirements, Fee and Inspection." Sulat.ph, updated November 21, 2026. https://sulat.ph/business/how-to/fire-safety-inspection-certificate
Free to quote with a link. For fees and deadlines, cite the law or the city ordinance named in the sources, with its date.
Author and editorial review
Deepak Middha, Chartered Accountant
Chartered Accountant with 18 years in hedge funds; writes and maintains sulat.ph. Every rate, ceiling, deadline and fee on this page is taken from the law, agency issuance or official local government page named in the sources and was checked against that source on November 21, 2026. Where a figure could not be confirmed officially, the page says so.
Author of The Complete Fund Accounting Handbook in the Sulat.ph Library
Spotted an error or an outdated rule? Send a correction.